Access Control Process - Keys/FOBs/Campus ID Cards
Project Scope:
Review and standardize the current "Building Access Request" processes relating to
FOBs, cards and metal keys. Using the current online form for building access request
as a guide, develop a process for Physical Plant to use when metal key request are
submitted, including automated e-mail notifications to be sent to appropriate department
designees, and a portal for viewing, managing and granting authorizations. Team will
review and recommend changes for policy UM1567 relating to Building Access/Key Control.
For questions and issues please contact Physical Plant Work Control at workcontrol@memphis.edu
PROPOSED TIMELINE: October 2016 - May 2017
"AS IS" Mapping (Current State)
"TO BE" Mapping (Future State)
Project Updates:
- Project Outcomes Phase I - December 2017
- Project Outcomes Phase II - First Annual Audit 2019
1) Email communication was sent to all Faculty & Staff October 2019
2) Internal Audit presented at Focus on Finance December 2019 meeting
3) December 31 due date for submission - Spring 2021 - System enhancements
- Include card & Fob access list
- Allow Designees access to department data
- Financial Managers ability to validate & acknowledge employees completed audit
- Argos reports for Internal Audit
- April 26 - Faculty/Staff notified to complete their annual access audit
- May 10 - Finnacial Manager notified to review and acknowledge department employees completed audit
Project Team:
- Adam Mendez, Athletic Facilities
- Bruce Johnson, Physical Plant-Lock Shop
- Cathy Wilhelm, Team Lead, Philosophy
- Carol Laney, Process Improvement - Business Analyst
- Colette Williams, Process Improvement - Project Manager
- David Medlock, Physical Plant
- Diana Humphrey-McKee, Physical Plant
- Hermes Rosa, Physical Plant
- Kevin Langellier, Police Services
- Kim Josh, Enterprise Application Services
- Melissa Ramage, Enterprise Application Services
- Michelle Smith, Center Earthquake Research & Information (CERI)
- Ron Brooks, Physical Plant
- Ryan Seidner, Physical Plant
- Sara Hagan, Enterprise Application Services
- Terrence Bronson, Physical Plant-Lock Shop